More deliveries than usual over the next few weeks

We’ve got a lot happening on site over the next few weeks and that means we’ll have more deliveries than usual. We apologise in advance for the inconvenience these may cause. As always, we will endeavour to work as efficiently as we can, while keeping safety as a top priority.

We now have two cranes on site: one for the houses (background of photo) and the other for the apartments in the middle of the site (foreground). We expect to have deliveries going into our gates off Salcombe Road (Gates 3 & 4) and our gate in the middle of Airport Road (Gates 6 & 7).

You’ll also be able to spot a concrete pump in the middle of the picture, which is filling in the bridge abutments.